I'm cutting and pasting this from a longer SEPTA press release:
SEPTA was awarded a $2.2 million competitive grant from Federal Transit Administration for the project. These funds will cover the vast majority of the $2.4 million estimated costs.
The Parkside Bus Loop serves routes 40, 43, 64 and 52 at 49th Street and Parkside Avenue, where it has been for some 90 years. The infrastructure is long past its useful life, and changes in the neighborhood have made the location obsolete for a bus loop. The new facility on North 50th Street will be near the heart of recent development, including the Park West Town Center.
Construction is expected to take approximately eight months, with major work completed by December 2011. The new facility will include state-of-the-art passenger amenities, safety features and will be fully accessible, per Americans with Disabilities Act (ADA) requirements
Tuesday, April 26, 2011
SEPTA's New Parkside Bus Loop